Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,496 questions

5,898 answers

1,321 comments

Register its Free

Download here

How is a compensation event handled if the Contractor has not submitted a quotation and details of his assessment within the time allowed?

0 votes
327 views
How is a compensation event handled if the Contractor has not submitted a quotation and details of his assessment within the time allowed?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  
edited Oct 9, 2012 by Chris Corr

1 Answer

0 votes
 
Best answer

The Project Manager will assess the compensation event (see Clause 64.1).

answered Oct 9, 2012 by BuiltIntelligence (870 points)