What happens if a change to the Works Information makes the description of the Condition for a Key Date incorrect?

0 votes
324 views
What happens if a change to the Works Information makes the description of the Condition for a Key Date incorrect?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (840 points)  

1 Answer

0 votes
 
Best answer

The Project Manager corrects the description. This correction is taken into account in assessing the compensation event for the change to the Works Information (see Clause 63.9).

answered Oct 9, 2012 by BuiltIntelligence (840 points)