Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,337 questions

5,718 answers

1,266 comments

Register its Free

Download here

What happens if a change to the Works Information makes the description of the Condition for a Key Date incorrect?

0 votes
330 views
What happens if a change to the Works Information makes the description of the Condition for a Key Date incorrect?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The Project Manager corrects the description. This correction is taken into account in assessing the compensation event for the change to the Works Information (see Clause 63.9).

answered Oct 9, 2012 by BuiltIntelligence (870 points)