If a compensation event includes a change to the Works Information provided by the Employer, how is the event assessed?

0 votes
333 views
If a compensation event includes a change to the Works Information provided by the Employer, how is the event assessed?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  
edited Oct 9, 2012 by Chris Corr

1 Answer

0 votes
 
Best answer

The effect of the event is assessed as if the Prices, the Completion Date and the Key Dates were for the interpretation most favourable to the Contractor (see Clause 63.8).