When does the Contractor’s title to Plant and Materials which are outside the Working Areas pass to the Employer?

+1 vote
439 views

 When does the Contractor’s title to Plant and Materials which are outside the Working Areas pass to the Employer?

asked Oct 15, 2012 in Title by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

Once the Supervisor has marked Plant and Materials which are outside the Working Areas, title to these items passes from the Contractor to the Employer (see Clause 70.1).

answered Oct 15, 2012 by BuiltIntelligence (870 points)  
edited Oct 23, 2012 by Rob Glasspool