Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,103 questions

5,447 answers

1,166 comments

Register its Free

Download here

If a compensation event arises from ambiguities or inconsistencies in the Works Information, how is the event assessed?

0 votes
360 views
If a compensation event arises from ambiguities or inconsistencies in the Works Information, how is the event assessed?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (840 points)  

1 Answer

0 votes
 
Best answer

The event is assessed as if the Prices, the Completion Date, and the Key Dates were for the interpretation most favourable to the Party which did not draft the Works Information (see Clause 63.8).

answered Oct 9, 2012 by BuiltIntelligence (840 points)