If a compensation event arises from ambiguities or inconsistencies in the Works Information, how is the event assessed?

0 votes
365 views
If a compensation event arises from ambiguities or inconsistencies in the Works Information, how is the event assessed?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The event is assessed as if the Prices, the Completion Date, and the Key Dates were for the interpretation most favourable to the Party which did not draft the Works Information (see Clause 63.8).