Does the assessment of a compensation event include an allowance for risk?

0 votes
458 views
Does the assessment of a compensation event include an allowance for risk?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

Assessment of the effect of a compensation event includes risk allowances for cost and time for matters which have a significant chance of occurring and are at the Contractor’s risk under this contract (see clause 63.6)

answered Oct 9, 2012 by BuiltIntelligence (870 points)