How is a delay to a Key Date assessed?

0 votes
342 views
How is a delay to a Key Date assessed?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (840 points)  

1 Answer

0 votes
 
Best answer
A delay to a Key Date is assessed as the length of time that, due to the compensation event, the planned date when the Condition stated for a Key Date will be met is later than the date shown on the Accepted Programme (see clause 63.3).
answered Oct 9, 2012 by BuiltIntelligence (840 points)