How is a delay to the Completion Date assessed?

0 votes
360 views
How is a delay to the Completion Date assessed?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

A delay to the Completion Date is assessed as the length of time that, due to the compensation event, planned Completion is later than planned Completion as shown on the Accepted Programme (see clause 63.3).

answered Oct 9, 2012 by BuiltIntelligence (870 points)