NEC3 ECC: Cost for producing quote that is not moved forward

+1 vote
310 views
On a ECC (3) option C contract if the Project Manager ask the Contractor to submit a quotation for a proposed instruction  and after he receives the quotation decides not to go ahead with the work can the contractor put in a notification of a compensation event to pay for the staff time in producing the quotation  should the Project manager agree and raise the target cost for the amount of the NCE?
asked Apr 23, 2015 in Compensation Events by anonymous   7 39 57
recategorized Apr 23, 2015 by Glenn Hide

1 Answer

+1 vote