What happens if a compensation event reduces the total Defined Cost?

+1 vote
376 views
What happens if a compensation event reduces the total Defined Cost?
asked Oct 9, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The Prices are not reduced except as stated in the contract (see clause 63.2).

answered Oct 9, 2012 by BuiltIntelligence (870 points)