Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,163 questions

4,330 answers

492 comments

34,123 users

Register its Free

Download here

NEC3 ECC: Cl. 61.4 The Contractor MAY notify the Project Manager... What if he doesn't?

+1 vote
495 views
Cl. 61.4 ....If the Project Manager does not notify his decision (as to whether a CE is indeed a CE) to the Contractor within (1 week) the contractor may notify the Project manager to this effect. A failure by the Project manager to reply within two weeks of this notification is treated as acceptance by the project manager that the event is a compensation event...

In the above clause the Contractor MAY notify the project manager, ‘may’ is not obligatory, so if he does not notify the Project Manager is the CE a CE by default or not?
asked Apr 10, 2015 in NEC3 Compensation Events by Aramis Tonks  
   

1 Answer

+2 votes
The word "may" is used as it does not make it obligatory to notify the Project Manager that he has failed to respond, but if the Contractor does not notify this then they can not  trigger the "deemed acceptance" loop which makes it deemed accepted if the fail to respond to the notification (that they have not responded). It is the Project Manager who has failed here.

If they fail to notify then it remains not agreed yet that this is a compensation event and the Contractor can not move forward with the quotation and is not clear on their likely liability.  

This same loops appears when the Project Manager fails to respond to a quotation, or fails to make their own assessment when they said they would. In each of these instances the Contractor can remind(notify) of the PM's failure to respond and after a further two weeks of silence their original quotation and assessment on time would now be deemed accepted by default.

These are the only three deemed acceptances in the whole of the contract and is trying to give the Contractor some recourse if the PM fails to carry out their contractual obligations.
answered Apr 12, 2015 by Glenn Hide (28,040 points)  
Glenn is exactly right. This is a great example of two wrongs don't make a right or, alternatively, the application of the principles of 10.1.