Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,200 questions

4,375 answers

511 comments

34,509 users

Register its Free

Download here

NEC3 ECC: Working weeks

+1 vote
220 views
Under option C, if the working weeks are not clearly stated in the contract and the latest accepted programme shows an allowance for holidays, can the PM reduce the time allowed for holidays in the latest programme submit for approval?
asked Mar 26, 2015 in NEC3 Time by anonymous  
   

1 Answer

+1 vote
The Project Manager could restrict a Contractor's working time (which would likely be a compensation event) but not really force him to work a shorter holiday. At the end of the day it is up to the Contractor when they want to work in order to meet the Completion Date - and if they are late they will be charged Delay Damages.
answered Mar 27, 2015 by Glenn Hide (29,340 points)