Where in NEC3 ECC is the best place to put design documents from a previous design contract, when the Contractor and the designer are the same company? ie do we include the drawings in CDP1 as Works Information or CDP2 as Contractor’s Works Information?
1 Like
Definitely the Contractor’s Contract Data part 2 as :
a. if there is an ambiguity or inconsistency within the documents they have generated, then it is their liability and it assumes they have priced on the more favourable circumstance to you ; and
b. if there is an ambiguity between it and the Employer’s Works Information, then the Employer’s Works Information takes precedence.