Do X5 Liquidated Damages or Delay Damages have VAT charged to them when applied under NEC3?

+2 votes
1,329 views
Do X5 Liquidated Damages or Delay Damages have VAT charged to them when applied to the Project Manager's assessment under NEC3?
asked Jul 24, 2013 in NEC3 Secondary X, W & Y options by anonymous  
   

1 Answer

+1 vote
See link below. In short, liquidated damages are outside scope of VAT.

http://www.hmrc.gov.uk/manuals/vatscmanual/vatsc35600.htm
answered Jul 24, 2013 by Chris Corr (6,660 points)