Do late adjudication decisions retain validity?

0 votes
367 views
asked Feb 6, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
All decisions are supposed to be reported within a 28 day period. While there may be a little leeway for some delay, this should not be undue and decisions must be delivered with the greatest amount of practicable speed if they overshoot this 28 day period.
answered Feb 6, 2013 by JCT Experts (-20 points)