Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

3,979 questions

4,116 answers

420 comments

33,479 users

Register its Free

Download here

If there is an adjudication decision with obvious calculation errors, is there any course of action possible other than arbitration?

0 votes
257 views
asked Feb 6, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
Yes, generally speaking, however an amendment via the 'slip rule' by the adjudicator will alter the situation. This simply gives the adjudicator the power to correct any small errors that he finds, so calculation errors can be included under this providing they are superficial in nature.
answered Feb 6, 2013 by JCT Experts (-20 points)