Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,161 questions

4,324 answers

491 comments

34,072 users

Register its Free

Download here

When a referral is made, is it legally permissible for the architect to respond on behalf of the employer?

0 votes
274 views
asked Feb 6, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
No, or at least it shouldn't be expected. The architect's duties do not include running an adjudication, nor do his / her skills or training indicate that this would be appropriate.
answered Feb 6, 2013 by JCT Experts (-20 points)