Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,085 questions

4,241 answers

450 comments

33,729 users

Register its Free

Download here

With regards to adjudication, are the various time periods of significance?

0 votes
251 views
asked Feb 6, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
Yes, in fact there is a very strict timetable regarding adjudication that must be obeyed. The basic time periods involved in adjudication are covered by the Housing Grants, Construction and Regeneration Act 1996, but the Scheme for Construction Contracts (England and Wales) Regulations 1998 may add additional time to the timetable.
answered Feb 6, 2013 by JCT Experts (-20 points)