Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,161 questions

4,324 answers

491 comments

34,072 users

Register its Free

Download here

If an adjudicator is appointed without the approval of the employer, does the employer have any recourse?

0 votes
252 views
asked Feb 6, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
Providing that the adjudicator has been appointed in accordance with the strict legislative procedure that has been laid down explicitly, then there is nothing the employer can do about the appointment of an adjudicator.
answered Feb 6, 2013 by JCT Experts (-20 points)