Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

3,979 questions

4,116 answers

420 comments

33,479 users

Register its Free

Download here

If a contractor runs over time and an architect over-certifies, will there be any legal issues should the employer desire to terminate the contract?

0 votes
251 views
asked Feb 6, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
All the standard forms of contract state explicitly that the architect is only permitted to certify amounts that are properly due, therefore in this scenario the architect has acted in breach of contractual obligations. There will certainly be problems in the case of termination, as the situation needs to be rectified during the issuance of the next certificate.
answered Feb 6, 2013 by JCT Experts (-20 points)