Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,161 questions

4,324 answers

491 comments

34,072 users

Register its Free

Download here

Is it legally permissible for an employer to take partial possession of a building so that an architect has no compunction to certify practical completion?

0 votes
566 views
asked Feb 6, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
This is dependent upon contractual terms. Under JCT Standard Building Contract 2009, JCT Design and Build Contract, JCT Intermediate Building Contract 2009 and JCT Intermediate Building Contract with Contractor’s Design 2009, it is permitted for an employer to take partial possession of any part of the Works on the condition that the contractor is agreeable. Once partial possession has been undertaken, it is considered that practical completion has occurred with regards to those specific parts of the building.
answered Feb 6, 2013 by JCT Experts (-20 points)