After termination, is the contractor entitled to a certificate of practical completion?

0 votes
284 views
asked Feb 6, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
No, this will be issued to whichever contractor takes over the work, if any.
answered Feb 6, 2013 by JCT Experts (-20 points)