ReachBack
After termination, is the contractor entitled to a certificate of practical completion?
JCT Contracts
JCT_Experts
6 February 2013 09:33
2
No, this will be issued to whichever contractor takes over the work, if any.
Related Topics
Topic
Replies
Views
Activity
JCT: Practical Completion for Sectional Completion Contracts
General
2
648
23 April 2020
JCT: When you have issued all the required Section Completion Statements, do you need to issue a Practical Completion Statement
JCT Contracts
3
551
3 June 2020
What is an architect's legal course of action if a contractor fails to provide final documents within the time period contractually specified, after practical completion has taken place?
JCT Contracts
1
430
5 February 2013
Construction law under the JCT
JCT Contracts
1
594
10 April 2017
Webinar - Overview of Partial Possession and Practical Completion under JCT D&B Contract
JCT Contracts
10
925
28 February 2024