Is it legally permissible for a contractor to make a loss and / or expense claim under JCT Minor Works Building Contract 2009?

0 votes
844 views
asked Feb 5, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
No. There is only a singular clause in JCT Minor Works Building Contract 2009 that refers to loss and / or expense, namely clause 3.6.3. There is no mechanism under JCT Minor Works Building Contract 2009 for a contractor to make such a claim.
answered Feb 5, 2013 by JCT Experts (-20 points)