Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,087 questions

4,242 answers

450 comments

33,754 users

Register its Free

Download here

Is it legally valid to claim increased costs by referring to national indices?

0 votes
178 views
asked Feb 5, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
No. In a claim for costs the onus is on the contractor to demonstrate that the increase in costs has been the direct consequence of the incidents cited by the contractor, and there is also a legal requirement to calculate the precise amount of loss and expense.
answered Feb 5, 2013 by JCT Experts (-20 points)