Why is it problematical to launch a successful claim for overheads and profit?

0 votes
201 views
asked Feb 5, 2013 in JCT Contracts by JCT Experts (-20 points)  
   

1 Answer

0 votes
This is because in order to make a claim involving either of these elements it is necessary to identify the specific amounts that were actually involved, and avoid all theoretical and / or assumed levels. This can be logistically very difficult to accomplish.
answered Feb 5, 2013 by JCT Experts (-20 points)