Does the Contractor’s acceptance of an insurance policy or certificate provided by the Employer change the responsibility of the Employer to provide the insurances stated in the Contract Data?
1 Like
No. The Employer’s responsibility to provide insurances stated in the Contract Data does remains unchanged on the Contractor’s acceptance of an insurance policy or certificate provided by the Employer (see Clause 87.2).