What happens if TRA (Time Risk Allowance) is not needed by the Contractor?

What happens if TRA (Time Risk Allowance) is not needed by the Contractor?

It will be converted to total float for non-critical activities and will bring forward planned Completion for the critical path items creating terminal float.