What should a Party do if he has more than one reason for withholding payment under Option Y(UK)2?

What should a Party do if he has more than one reason for withholding payment under Option Y(UK)2?

If there is more than one reason for withholding payment, the amount withheld for each reason should be stated in the notification (see Clause Y2.3).