Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,238 questions

4,422 answers

537 comments

34,652 users

Register its Free

Download here

NEC ECC: Do limitations of liability in X18 extend to capping liability to Delay Damages?

+1 vote
48 views
asked Oct 5 in NEC3 Secondary X, W & Y options by Glenn  
   

2 Answers

+1 vote
 
Best answer
No, they are explicitly excluded in clause X18.4, second bullet.
answered Oct 5 by Jon Broome (23,650 points)  
selected Oct 5 by Glenn Hide
+1 vote
It would depend upon the wording in your contract.  Start by looking at whether Secondary Options X7 and  X18 have been amended from the standard text and then see what Contract Data Part 1 states about these options, which should clarify the situation.

A common approach is capping liability for delay damages at, say, 15% of the total of the Prices at the contract date and to 100% of the total of the Prices at the contract date, for aggregate liability.
answered Oct 5 by Andrew WI (2,200 points)