Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,238 questions

4,422 answers

537 comments

34,652 users

Register its Free

Download here

NEC ECC: Is there any status of exceptional acceptance of programme.

+2 votes
65 views
Can a programme accepted as accepted with exception (except as note) can be treated as accepted programme and be used a basis for analysis of CE.
asked Sep 15 in NEC3 Time by imran (140 points)  
   

2 Answers

+4 votes
Yes - but depends on the wording here. I would much prefer "acceptance with comments" than exceptions. I am actually a strong advocate of "acceptance with comments", the comments being relatively small issues which are not big enough issues to reject now but need resolving. For example it may be that an element needs breaking down into more detail, but that item is some way in the future. There may be some minor issue with logic but would not affect the critical path.

Acceptance is acceptance so it should be used to assess the CE against. The only case I would not advocate is where the exceptions are for major elements that are wrong - like wrong sequence on critical path, wrong Completion Date etc.
answered Sep 15 by Glenn Hide (30,630 points)  
+2 votes
Imran,

I would agree with Glenn - An accepted programme is just that, accepted. The 'exceptions' - or comments should only be minor issues. I too agree with accepting with comments to prevent minor issues getting in the way of programme acceptances. Major issues should be avoided when accepting programmes.
answered Oct 9 by KMP2017 (300 points)