Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,236 questions

4,421 answers

536 comments

34,651 users

Register its Free

Download here

NEC ECC: Final Account time frame.

+1 vote
96 views
What is the time frame for  the QS  to complete the final account since final completion has been granted. He had all the information required to complete the final  account. From when are you  entitled to interest on the outstanding money owed?  The amount outstanding is about 10% of the contract amount.
asked Aug 4 in NEC3 Time by anonymous  
   

1 Answer

+1 vote
The normal payment timescales - i.e. the assessment interval - and mechanisms continue on after the Completion Date. So if you make an application and claim the full amount, the the PM will, in his assessment, have to give reasons for deducting those amounts.

If you disagree with those amounts, a dispute has crystallised, so you could go to Adjudication, which I would only advise doing so after trying to escalate it to the PM and then the Employer.

A more fruitful avenue might be this : you are entitled to interest on the amounts from when they became due provided you applied for them i.e. a mistake by the PM (see clause 51.3) , so you could include in your application interest on these outstanding amounts from the time that you starting applying for them. That - along with a word to the PM -  might nudge the QS in the direction you want.
answered Aug 7 by Jon Broome (23,650 points)