Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,236 questions

4,421 answers

536 comments

34,651 users

Register its Free

Download here

NEC ECC: Process to implement Clause X1 where no indices have been included?

+1 vote
67 views
We are currently working on a JV project which has clause X1 included in the contract documentation. We are aware that indices should be written into contract data part 1 but this has been overlooked, What is the best way to progress considering there is no information included within the contract?
asked Aug 4 in NEC3 Secondary X, W & Y options by Jack   1
   

1 Answer

+1 vote
From what you say, it is clear that price adjustment for inflation is part of the contract.

So choose an indices that you like and propose it to the PM / Employer. See what they come back with !
answered Aug 7 by Jon Broome (23,650 points)