NEC ECSC: Can a Compensation Event occur after defects date

0 votes
74 views
We have completed a project under ECSC contract and the defects date has now passed but an event has occurred which would ordinarily be a CE under clause 60.1(14).

I appreciate that clause 61.5 states that "A compensation event is not notified after the defects date", however is there any mechanism which would allow this event to be considered or notified as a CE after the defects date.
asked Aug 4 in NEC3 Compensation Events by Sean (120 points)  
   

1 Answer

0 votes
As you state clause 61.5 sets out that a CE is not notified after the defects date however if both parties are in agreement to have the work carried out then clause 12.3 can be used to record the agreement.
answered Aug 4 by dave bates (5,050 points)