Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,161 questions

4,330 answers

491 comments

34,091 users

Register its Free

Download here

JCT - Client changing specifications - what can I claim?

0 votes
29 views
The contract is a fixed cost jct the client is out sourcing different specifications from the contract i.e. Cheaper bathrooms cheaper floor finishes and external cladding we are still applying ohp to the new specifications but the changes are having a huge impact on the over all contract value. Can I claim the original ohp from the original specifications I understand the Client needs the right to change there mind on specifications
asked Jul 22 in NEC3 Time by Sean   2
   

Please log in or register to answer this question.