NEC PSC: Change in skill level of a resource

+1 vote
45 views
A consultant has requested to increase a skill level of a resource in an option G contract since he has taken up more responsibility in the project, how does one handle this change within the contract
asked Jul 6 in NEC3 General by NP (170 points)  
   

1 Answer

+1 vote
Presumably, an increased level of skill resource is because the Consultant is now being instructed  to do something that was not in the original Scope. I.e. there is a change in Scope which is a compensation event.
answered Jul 7 by Jon Broome (23,720 points)  
Thanks Jon, There is no instruction to the Consultant for additional work. His rationale is that the particular resource has taken more responsibility within the project hence the need to elevate him