Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,132 questions

4,298 answers

475 comments

33,914 users

Register its Free

Download here

NEC ECS: Sub-subcontractor costs

+1 vote
35 views
When valuing CE's which include a sub sub contractors costs, should the sub sub contractors costs be exclusive of their overhead & profit and deemed to be included in the sub contracted fee in the Contract Data Part 2?
asked Jun 21 in NEC3 Compensation Events by anonymous  
   

1 Answer

+1 vote
Depends from where you are looking at it from and which option the main Contractor is on, the Subcontractor is on and the sub sub contractor is on ! Please clarify !
answered Jun 21 by Jon Broome (20,380 points)