NEC ECS: Sub-subcontractor costs

+2 votes
47 views
When valuing CE's which include a sub sub contractors costs, should the sub sub contractors costs be exclusive of their overhead & profit and deemed to be included in the sub contracted fee in the Contract Data Part 2?
asked Jun 21 in NEC3 Compensation Events by anonymous  
   

1 Answer

+2 votes
Depends from where you are looking at it from and which option the main Contractor is on, the Subcontractor is on and the sub sub contractor is on ! Please clarify !
answered Jun 21 by Jon Broome (22,080 points)