Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,087 questions

4,242 answers

450 comments

33,755 users

Register its Free

Download here

NEC ECC: Compensation Event without an accepted first programme of the Contract

+1 vote
73 views
How do you assess a Compensation Event when the first program of the contract hasn't been accepted - the contract has no program yet.
asked May 24 in NEC3 Compensation Events by anonymous  
   

1 Answer

+1 vote
With difficulty !

The first thing to say is that the financial assessment is not directly linked to having an Accepted Programme as it is not mentioned in the key clause of 63.1. So in assessing the financial aspects, you can make reference to the submitted programme and the impact etc on method, time scales, use of resources, time in the Working Areas, risk and cost (in approx. that order).

It does become more tricky with assessing the time and contractually changing the Completion Date as clause 63.3 does make direct reference to the Accepted Programme as the reference point for how change is evaluated. Here I hope some common sense prevails in that if, for instance, the PM has accepted the change in Defined Costs is partly made up of changed costs for prelims of, let's say a week, then he or she would be inconsistent in saying that the CE has not had that same affect wrt to the Completion Date.

But strictly b y the contract, that does not matter. Having said that, the latest case law on NEC seems to indicate that the courts don't care what the contract says ! See my comment here : https://www.linkedin.com/groups/2893228/2893228-6271255410993299458
answered May 24 by Jon Broome (18,240 points)