NEC 3 Options A,B,C & Short - When we submit a technical submission with our tender, which is scored, does the information that we provide form part of the contract or is it just for information and evaluation purposes.
1 Like
It depends on whether it is is incorporated into the contract by reference from the Contract Data. If it is, then there can be no doubt.
If it isn’t, then there might be arguments about intentions of parties etc. which will hinge on the correspondence before the contract.