Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,240 questions

4,428 answers

540 comments

34,653 users

Register its Free

Download here

NEC ECC: Failure to commence work due to community problems.

+1 vote
61 views
Starting date was defined as the date that the Contractor receives a fully signed copy of the contract. Access to site was scheduled within 2 weeks of the starting date. Site handover was conducted within 2 weeks of the starting date. However, the Contractor experienced community problems on site since the community raised issues that they were not included during the whole tendering and contract award process, thereby the Contractor could not start work on site. The Contractor issued an early warning to the PM, and the matter was closed 3 - 4 weeks later. Which Compesation event is this one?
asked May 10 in NEC3 Compensation Events by anonymous  
   

1 Answer

0 votes
It sounds like a clause 60.1(19) event has most likely happened.
answered May 11 by Neil Earnshaw (6,620 points)