Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,240 questions

4,426 answers

538 comments

34,652 users

Register its Free

Download here

NEC ECC: Can Delay Damages be changed by agreement between the parties under clause 12.3

+2 votes
90 views
I think it is fair to say that anything in the contract can be changed by agreement (as long as agreement means both Parties agreeing!). You may need to take legal advise as to how this is written and signed to make sure it is binding. If it suits both Parties that an aspect of the contract changes then the contract would not want to prevent this.
asked May 8 in NEC3 Contract Data by anonymous  
   

1 Answer

+1 vote
Yes, as you have rightly stated above, you can change anything by agreement between the Employer and the Contractor provided you comply with clause 12.3 and aren't doing anything illegal.
answered May 11 by Neil Earnshaw (6,620 points)