Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,091 questions

4,244 answers

451 comments

33,760 users

Register its Free

Download here

NEC ECC: Can a Project Manager "unaccept" an Accepted Programme?

+1 vote
62 views
What are your thoughts on the question of the PM having accepted a programme that subsequently is shown to be contra the contract requirements? Can the PM withdraw acceptance? The Contractor is, at the moment, unwilling to correct and is using the (erroneous) acceptance to claim the requirements of the contract have changed and therefore the contract is acceptable now
asked Apr 21 in NEC3 Time by anonymous  
   

1 Answer

+1 vote
Bad news is that you can't withdraw acceptance of the last programme. The good news is that they HAVE to submit a revised programme at the interval stated in contract data part 1 (normally every 4 weeks or every month) and now you can reject their next one as it would not be either practicable or reflect their plans realistically. If you have rejected their last programme then you can make your own assessment of any future compensation events - including what effect you believe this will now have on their programme.
answered Apr 21 by Glenn Hide (27,180 points)  
The PM can change his mind, but not without redress. Clause 60.1(8) deals with the PM or Supervisor changing a decision they have previously communicated to the Contractor. Accepting or not accepting a programme is one of the PM's most important decisions.