Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,283 questions

4,472 answers

579 comments

34,694 users

Register its Free

Download here

NEC ECC: DOES THE APPRENTICE LEVY QUALIFY UNDER NEC3 X2

+1 vote
103 views
AS a contractor does the Apprentice Levy qualify as a rechargeable expense under X2
asked Apr 11 in NEC3 Secondary X, W & Y options by JPD (130 points)  
   

1 Answer

+2 votes
My view is yes the apprentice levy is a change in law (UK).

 It is new legislation that has been introduced in the Finance Bill where there was no existing legislation.
answered Apr 11 by dave bates (5,130 points)  
One minor point to bear in mind is that the levy will only be a compensation event for contracts entered into before the 6th April 2017 as X2 uses the term Contract Date to draw a line in the sand.