NEC TSC: Are weather events Employer risk or Contractor risk?

+1 vote
95 views
NEC TSC: Are weather events Employer risk or Contractor risk?

I've been reading through the compensation events and the risks at 80 and 81 but i can't clearly determine whether weather risk belongs to the Contractor or not.  I would say that it is as it's not clearly set out as a compensation event or an Employer risk but is it really that simple?

I'm also thinking that it's clearly set out in ECC therefore its absence in TSC indicates to me that it's not a compensation event.

Many thanks
asked Mar 31 in NEC3 and NEC4 Contracts by anonymous  
   

1 Answer

+1 vote
You are correct, weather is not a CE so should be thought of as a Contractor's risk
answered Mar 31 by dave bates (5,050 points)