Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,200 questions

4,375 answers

511 comments

34,509 users

Register its Free

Download here

NEC3 ECC: When Substantiating CE's are Site diary’s sufficient for backing up Labour onsite and time taken for tasks?

0 votes
113 views
I have several CE’s on a project where I have used the site diary to substantiate the Labour being used and time taken for the task, I’m being told that because this has not been signed by our client they can’t be used for back up. Also when I have given them Invoices for Plant and Materials used they are asking how they know the plant and materials were actually used for that task.

A lot of the CE’s were quoted upfront and rejected mainly on the duration required for the task. We had got on with the work in order not to delay the programme.

Can i use site diary's and invoices they have always been accepted before? the contract is unamended Option B
asked Mar 15 in NEC3 Compensation Events by Pete.conway (150 points)  
   

1 Answer

0 votes
Whilst things like site diary sheets and invoices are all important records for a Contractor - they have very little relevance when it comes to assessing compensation events. Clause 63.1 states that you use actual Defined Cost for work already done, forecast Defined Cost for works not yet done plus fee. The important switch point between actual and forecast is when the PM gave the instruction to change Works Information, or for all other events when the compensation event was notified. Therefore the majority of compensation events should be based upon a forecast of what would have been reasonable (including sensible allowance for risk). Just because you have done the work before the quote has been agreed does NOT mean that you revert to actual cost - hence I see no significance for diary sheets etc.

Hindsight should not come into the assessment! Even if you have diary sheets showing it took ten men ten days to do an activity - who's to say they did not go slow and drag it out? On the other side an Employer might say "why should I pay for risk that I can see did not happen?"  Well, the answer is that for the same reason the Contractor can not claim for more risk than they allowed for in their quote if it was worse and it has not yet been agreed.
answered Mar 16 by Glenn Hide (29,340 points)