Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,143 questions

4,307 answers

482 comments

33,960 users

Register its Free

Download here

NEC3 ECC: Option A - Activity Schedule

+1 vote
198 views
If an item of work is included within the Contractors Activity schedule but that item has not been carried out on site; how do we deal with the financial side of this issue:
a. Presumably it cannot be included in the PWDD
b. At the end of the job after handover should I include it in the assessment for payment
or c. The contractor does not get paid at all
Could you consider this issue if a. it is specifically included within the EMPLOYERS works information b. It is specifically included in the Contractors works information only c. not included in either works information
asked Mar 15 in NEC3 Payment by anonymous  
   

1 Answer

+1 vote
The Contractor should revise their activity schedule and spread that cost elsewhere within the other items on the activity schedule. It is a lump sum fixed price. If an item is not done it does not mean the Employer does not pay it - likewise if a Contractor does double what they thought of an item on the activity schedule they cant claim extra as a change in activity schedule alone is not a CE.
answered Mar 15 by Glenn Hide (27,780 points)