NEC3 ECC: Rejecting Contractor design

0 votes
68 views
Assuming the Contractor's design complies with Works Information and the applicable law; can Project Manager reject it? If so what are the implications?
asked Mar 15 in NEC3 Compensation Events by dayIn (120 points)  
recategorized Mar 15 by Glenn Hide
   

1 Answer

0 votes
PM can always reject for any reason, but if not a valid reason in the contract then this would become a compensation event under 60.1(9). Any rework of the design and any associated implications would be assessed within that compensation event.
answered Mar 15 by Glenn Hide (27,100 points)