Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,044 questions

4,189 answers

430 comments

33,574 users

Register its Free

Download here

NEC3 ECC: Decloration of savings under option C

+1 vote
60 views
If a Contractor wants to use a Subcontractor with a slightly different design but conforms with the Works Information and a cheaper option, with option C and with X15 do they have to declare the savings?
asked Mar 8 in NEC3 Payment by anonymous  
   

1 Answer

+1 vote
X15 is irrelevant in this particular situation. It depends if the design is your responsibility or it is the Employers. If it is Contractor design and they propose a value engineering idea, then this is an exception to 60.1(1) being a compensation event - meaning this value engineering idea will NOT change the total of the Prices (target) and both Parties will benefit from the saving. If the alternative subcontractor/design complies with Works Information there should be no reason to say no (and why would the Employer if they would benefit from the saving?)
answered Mar 16 by Glenn Hide (26,200 points)