Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,087 questions

4,242 answers

450 comments

33,755 users

Register its Free

Download here

JCT: If a CA does not ask for further information in respect of a delay notice until after 12 weeks from when the delay notice was issued, does the 'actual' 12 weeks from receipt of the required particulars begin when the Contractor responds to the CA's request?

+1 vote
47 views
The Contractor issued a delay notice which included numerous possible delay events and the CA did not request any further details of the events until about 16 weeks after the delay notice had been issued.  Within 2 weeks of the CA's request, the Contractor provided further information.  The position which is unclear is whether the 12 week period began when the contractor's further information was provided following the CA's requests and what the implication is that the CA did not request any information within 12 weeks of receiving the delay notice.
asked Mar 8 in JCT Contracts by anonymous  
   

1 Answer

+1 vote
If the delay notice is properly given under clause 2.24 then that is the date from which the 12 weeks runs. However, the general argument often followed is that the original notice was defective as it did not contain the information which was later requested so it is only once that information is provided that the 12 weeks can start to run.

Under the JCT (unlike FIDIC perhaps) the basic requirements of the notice of delay or relatively simple and therefore the 12 weeks will almost always start to run on that date.

There remains the question of the consequence of not answering in 12 weeks as there is no default acceptance or loss so a failure to notify under 2.25.2 rarely goes anywhere.
answered Apr 10 by Rob Horne (8,850 points)