Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

4,087 questions

4,242 answers

450 comments

33,755 users

Register its Free

Download here

NEC3 ECC: Is there a provision in the NEC for a Contractor to be paid an advance payment for a provisional sum item in the boq?

+1 vote
92 views
asked Feb 21 in NEC3 Payment by anonymous  
   

1 Answer

+2 votes
NEC does not provide for provisional sums. The Works Information should be clear as to what is required so that it can be programmed and priced.

If the Employer is not sure what is required then he should set out clear assumptions in the Works Information that can be programmed and priced and should the assumptions change then the CE process kicks in.

There is provision under X14 for advanced payments.
answered Feb 21 by dave bates (4,230 points)  
You do indeed have a problem. As has already been stated NEC does not provide for provisional sums and as such there are no provisions dealing with the expenditure of these sums. If the works which they relate to are not covered in the Works Information then you are not obliged to do them. Clause 55.1 in main Option B clearly states that information in the Bill of Quantities is not Works Information or Site Information. You will therefore need a Project Manager's Instruction (clause 14.3) before carrying out any works related to these provisional sums which will then be a compensation event under clause 60.1(1) attracting any associated cost and time. You will then be paid for the work when it is completed.