Expert advice in minutes not days. Register it's free and ask your first question now.
  • Register
ReachBack is our free community help desk for construction professionals. A library of high-quality questions from real users with answers delivered and curated by a panel of industry experts.

3,979 questions

4,116 answers

420 comments

33,482 users

Register its Free

Download here

NEC3 ECC: Adding in terminal float on revised programmes

0 votes
106 views
Having already accepted a programme which showed no terminal float, the C has since completed certain critical path activities (with minimal TRA) and is now planning to complete two weeks ahead of the Completion Date.  He is now seeking to add a new activity to snap up these two weeks as terminal float.  Does the contract permit such approach or should the two week be shown as free float?
asked Jan 24 in NEC3 Time by anonymous  
   

1 Answer

+2 votes
The contract does indeed permit such an approach - although I don't feel this is a trick or a ploy on the Contractors part. At the end of the day, if they have not used all of the time risk allowances they had allowed for on the critical path then their planned Completion (which should be shown as a separate milestone) sounds in this case that it has moved forward by two weeks. This has created a difference of two weeks between "planned Completion" and the "Completion Date" which the guidance notes specifically calls "terminal float". The Contractor owns such float (like they do time risk allowances) and is retained in the assessments of future compensation events i.e. if a future CE moves planned Completion by one week Completion Date also moves by one week - maintaining the terminal float that has been created. If a Contractor suffers a one week delay which is their liability which moves planned Completion by one week then the terminal float period by default would now only be one week.  

Free float/total float is float on non-critical activities which is shared by both Parties but is not relevant in the example you give here.
answered Jan 24 by Glenn Hide (24,930 points)